Project Crashing



9-46



§



9-47



§



Time-Cost Relationship

—Crashing costs increase as project duration



decreases

—Indirect costs increase as project duration

increases

—Reduce project length as long as crashing costs

are less than indirect costs



9-48



§



Time-Cost Tradeoff



9-49



§



Microsoft Project

—Popular software package for project management



and CPM/PERT analysis

—Relatively easy to use



9-50



§



Microsoft Project



9-51



§



Microsoft Project



9-52



§



Microsoft Project



9-53



§



Microsoft Project – Zoom View



9-54



§



Microsoft Project – Task Information



9-55



§



Microsoft Project – Degree of

Completion



9-56



§